The project includes the retrieval of the damaged cable and termination, installation, trenching and commissioning of the replacement cable.
DOF’s contract scope includes project management, engineering, procurement and logics of cables and all associated equipment, as well as the complete offshore works.
Preparations have already commenced from DOF’s expert cable team across Aberdeen, Scotland and Bergen, Norway. Offshore execution is planned from March onward. The vessel Skandi Hera is scheduled as the installation vessel.
The value of the project is approximately USD 13 million.
DOF’s group CEO Mons S. Aase says, “This award demonstrates trust in DOF’s cable solutions within the renewable energy segment. We look forward to executing this highly important project to our highest standards.”